Thursday, May 31, 2012

A Quick Note

There have been no posts since Saturday because the guys have been working at the new hospital job site.  However, they should be back tomorrow and I'll update the blog after that.


In the meantime, the tiler and the electrician have continued to move ahead with their tasks.  The tiler is on the final room, so will be done either today or tomorrow.  Troy (electrician) will be here for awhile longer, running wires and hooking things up.  He probably has about 2 weeks of work left to do, mainly because he can only be here at night and on Sundays.  We've still got to finish a couple of things in my area before he goes, as well.


This blog will soon be finished and I'm not sure what all of you will then do with your lives.  Maybe I can think of something else to blog about and keep you people out of trouble!  Got any ideas?


Be sure to check back at some point over the weekend.  Until then, have a Bermudaful day.

Saturday, May 26, 2012

Weekend Post

Thought I'd wait until today to post and cover two days at once, since this was the first Saturday the guys have had a chance to work here for awhile.


Yesterday, the main focus was to dig a trench along the entire length of the driveway and across the front parking area to run the main water pipes to the pit.  By the end of the day, the trench was dug and all pipes were put in place.
Johnny begins digging the trench at the far end of the driveway
Chris drills a hole through the kitchen wall to join the drainage pipes to the main water pipes outside
Tony searches for the side wall of the pit
Johnny digs next to the pit location
Chris chisels into the side wall of the pit
Two holes have been cut out for access to both sections of the pit
A look at how the trench runs toward the pit
Johnny digs deeper to allow the water pipe to run downward to the pit
Ryan and Johnny fit the sections of pipe together
The guys check levels on the final section of pipe - the double running pee pee trap!


Johnny told me the actual name for that section of pipe, but I like my description much better!


This morning, the guys returned to cover up most of the trench, just leaving the main access points exposed for the Health Inspector to examine next week.  They also worked on sealing up the new doors and windows, as well as finish off a few minor plastering jobs.
Johnny starts the backfill process
Johnny packs down and levels the backfill as he goes along
All main access pipes remain exposed for inspection
Water pipes leading into each side of the pit, prior to being sealed up
Chris mixes up a batch of concrete to seal the holes in the pit
Chris forms up the concrete seal
The side of the pit is now sealed again
The trench has been backfilled and the driveway leveled off


During the past few days, the tiler has been here and the rooms are quickly being completed.  The painter and electrician have also been working in the evenings, so a couple more weeks and the kids should be ready to move in.


Be sure to check back on Monday for a further update!

Thursday, May 24, 2012

3 Weeks of Stuff!

I've had all sorts of email, asking for new posts to the blog.  Sorry it's taken so long, but I'll catch you up today.  It's May 24th, Bermuda Day, so only the tiler is working today - so far.  The painter and electrician may show up at some point, but we'll see.


The major renovations are just about finished and the contractor wanted to be out of here by the end of this week.  However, I think a couple of the guys will still be around for part of next week, finishing up some of the little things.


Although I didn't post to the blog, I continued taking pictures of the daily activity and will share most of them today.  After this, the only other major construction will be when the guys channel out the driveway and install water pipes, which will be attached to the pit in the front yard.


At this point, all of the new doors and windows have been installed.  The initial plan was to put a French door on the wall along the current driveway, but it was decided to put it at the front of the house instead.  This meant the outside access to the water tank had to be chopped down and the tank top cover now resides on top of a new outside step.


The inside walls of my previous office were chopped out and steel beams had to be inserted to take the load of the upstairs structure.  This resulted in a larger area for the new living room and an open plan to the new kitchen from there.


Okay, here come the pictures.  Enjoy!


Johnny, John Sr., Chris and Tony move the 18ft steel beam
Father and sons are all smiles as they move the steel beam into the house
Tony begins to block up the wall at the bottom of the steps, leading from upstairs to down below
The wall is halfway built
Almost done
The previous access is fully blocked
Ceiling supports are in place prior to the walls being chopped out
Chris demolishes one of the inside walls
Johnny removes rubble from the wall demolition
The rubble is loaded into the truck
The wall is mostly removed by the end of the day
Chris trims the edges of the larger wall, while Tony begins to chop out the smaller wall
Tony uses a maul to remove some of the block
Johnny and Tony jack hammer the wall from opposite sides
The guys clear the rubble after the wall is demolished
It looks like Ryan is waiting for an order of Tina's scalloped sweet potatoes at the kitchen take-out window!
Johnny digs around the outside water tank access
A closer look
Johnny has to use the jack hammer closer to the main house wall
Most of the block from the outside tank access cover is removed
The outside steps to my new office and radio room, before the railing is installed
After the railing has been installed
A front view of the railing installation
Johnny loads the truck with unused materials, prior to project completion
Starting to chop out the lower front windows
The lower front windows are removed
Framework started for the new front door
Using the bobcat to remove the old windows from the parking area
Loading the old windows into the truck
The new front entrance is boarded up for the night
Chris removes the last level of block from the tank access
Victor chisels the outside door entrance wall to prepare for plastering
Tony begins to remove one of the side windows
Chris takes out one of the side windows
The window is removed
Chris does some final chiseling of the tank access area
The old side window will be replaced with a door
A sliding glass door is installed for the master bedroom
Getting ready to install the new front door
John Sr. secures the new front door frame
The new front door is installed
John Sr. and Chris install the new side door
John Sr. and Chris check the door alignment
The new side door is installed
The old door has been removed and the area is prepared for a new window to be installed
The new window has been installed, at left, and another new window is being prepared for installation
Preparing to pour concrete for a front entrance step
Last section of the front entrance step being poured
Victor and Tony level off the front entrance step
The new front entrance step is complete
The new side windows and door installations are complete
Tony finishes plastering around the front entrance step


Now, you're up to date with the renovation progress.  I'll do my best to post the remaining outside work on a more timely basis, so keep checking back!