Thursday, May 24, 2012

3 Weeks of Stuff!

I've had all sorts of email, asking for new posts to the blog.  Sorry it's taken so long, but I'll catch you up today.  It's May 24th, Bermuda Day, so only the tiler is working today - so far.  The painter and electrician may show up at some point, but we'll see.


The major renovations are just about finished and the contractor wanted to be out of here by the end of this week.  However, I think a couple of the guys will still be around for part of next week, finishing up some of the little things.


Although I didn't post to the blog, I continued taking pictures of the daily activity and will share most of them today.  After this, the only other major construction will be when the guys channel out the driveway and install water pipes, which will be attached to the pit in the front yard.


At this point, all of the new doors and windows have been installed.  The initial plan was to put a French door on the wall along the current driveway, but it was decided to put it at the front of the house instead.  This meant the outside access to the water tank had to be chopped down and the tank top cover now resides on top of a new outside step.


The inside walls of my previous office were chopped out and steel beams had to be inserted to take the load of the upstairs structure.  This resulted in a larger area for the new living room and an open plan to the new kitchen from there.


Okay, here come the pictures.  Enjoy!


Johnny, John Sr., Chris and Tony move the 18ft steel beam
Father and sons are all smiles as they move the steel beam into the house
Tony begins to block up the wall at the bottom of the steps, leading from upstairs to down below
The wall is halfway built
Almost done
The previous access is fully blocked
Ceiling supports are in place prior to the walls being chopped out
Chris demolishes one of the inside walls
Johnny removes rubble from the wall demolition
The rubble is loaded into the truck
The wall is mostly removed by the end of the day
Chris trims the edges of the larger wall, while Tony begins to chop out the smaller wall
Tony uses a maul to remove some of the block
Johnny and Tony jack hammer the wall from opposite sides
The guys clear the rubble after the wall is demolished
It looks like Ryan is waiting for an order of Tina's scalloped sweet potatoes at the kitchen take-out window!
Johnny digs around the outside water tank access
A closer look
Johnny has to use the jack hammer closer to the main house wall
Most of the block from the outside tank access cover is removed
The outside steps to my new office and radio room, before the railing is installed
After the railing has been installed
A front view of the railing installation
Johnny loads the truck with unused materials, prior to project completion
Starting to chop out the lower front windows
The lower front windows are removed
Framework started for the new front door
Using the bobcat to remove the old windows from the parking area
Loading the old windows into the truck
The new front entrance is boarded up for the night
Chris removes the last level of block from the tank access
Victor chisels the outside door entrance wall to prepare for plastering
Tony begins to remove one of the side windows
Chris takes out one of the side windows
The window is removed
Chris does some final chiseling of the tank access area
The old side window will be replaced with a door
A sliding glass door is installed for the master bedroom
Getting ready to install the new front door
John Sr. secures the new front door frame
The new front door is installed
John Sr. and Chris install the new side door
John Sr. and Chris check the door alignment
The new side door is installed
The old door has been removed and the area is prepared for a new window to be installed
The new window has been installed, at left, and another new window is being prepared for installation
Preparing to pour concrete for a front entrance step
Last section of the front entrance step being poured
Victor and Tony level off the front entrance step
The new front entrance step is complete
The new side windows and door installations are complete
Tony finishes plastering around the front entrance step


Now, you're up to date with the renovation progress.  I'll do my best to post the remaining outside work on a more timely basis, so keep checking back!

4 comments:

  1. Nice! really coming together.

    ReplyDelete
  2. btw, Happy Bermuda Day! post facto ;-)

    ReplyDelete
  3. Looking good Glen :) Thanks for the update

    ReplyDelete
  4. I'm particularly fond of the art work - did you do it? lol

    Wow; I'm amazed on how much work is taking place...you'll have to do a virtual tour upon completion.

    ReplyDelete