It started out nice and sunny, first thing this morning, but soon turned cloudy and cool by noon.  I guess I should be wearing long pants, but am doing my best to keep the shorts going.


The guys continued preparing the roof/ceiling of the master bedroom for a concrete pour, which is planned for this Thursday.  Hopefully, the weather will cooperate that day.
Several cells were cut out along the outer wall of the main house
Getting things ready for the concrete pour
Johnny, John Sr. and Tony work on the metal rod supports
Johnny trims the metal rod supports
The metal rod supports are all in place


Once the work on the metal rod supports was done, the guys went to the new hospital project for the rest of the day.


Swanee arrived early this morning and continued tiling the stairs.  I took a peek downstairs, tonight, and everything appears to be completed.  Looks like I can start moving my things into the new rooms tomorrow, depending on the weather.


Troy stopped by at the usual 5:30pm time and began getting the electrical installation done for the master bedroom and bathroom, so the rooms can be ready for Thursday's concrete pour.  He was here until 9pm and will be back, tomorrow night, to finish off.