Mostly cloudy and wet this morning, so only inside work could be done.  Luis finished up the plastering of the doorways in the "dungeon," while Chris and Tony constructed formwork for the three windows.  Johnny installed PVC piping for the hot water heater, which will now be located at the back of the radio room.


Luis plastering the doorway to Jason's future "Man Cave"
Chris installing formwork for one of the windows
The guys finished up by noon and called it a day.  Tomorrow, they will be back at the new hospital location again, but will return on Wednesday morning.  Hopefully, the weather will be good again and the outside work can resume.


Troy turned up at the end of the afternoon and began to install the light fixtures in the radio room, as well as run the wiring for the lights and the water heater.


Troy installing the recessed lighting fixtures
The 4 recessed lighting fixtures.  The center box is for a ceiling fan.


A quiet beginning, however, there should be lots of progress by the end of the week as long as the weather cooperates.