Only 17 hours after the concrete top for the pit was poured! |
Pit access covers concreted with metal handles attached |
The pit is now covered and the parking area leveled off |
The remaining walls in the window-well were plastered and measurements were taken for the iron grating to sit on top of the opening.
Luis and Tony working on the window-well walls |
Tony plastering the window-well walls |
John taking measurements for the iron grating |
The master bedroom/bath area needed to be dug down a bit lower, then channels were cut out to make way for the water pipes to be placed.
John gives Johnny instructions for the additional digging requirements |
Digging deeper for the master bedroom/bath foundation |
The water pipes will be located in these channels |
The last task of the day was to form up the current downstairs steps to make them wider. Tomorrow, concrete will be poured and the additional area leveled off.
John watches as Chris creates the formwork for the steps |
Completed formwork - ready for concreting |
I'm hoping the weather will continue to be good tomorrow and allow for yet another productive day.