Only 17 hours after the concrete top for the pit was poured! |
![]() |
Pit access covers concreted with metal handles attached |
![]() |
The pit is now covered and the parking area leveled off |
The remaining walls in the window-well were plastered and measurements were taken for the iron grating to sit on top of the opening.
![]() |
Luis and Tony working on the window-well walls |
![]() |
Tony plastering the window-well walls |
![]() |
John taking measurements for the iron grating |
The master bedroom/bath area needed to be dug down a bit lower, then channels were cut out to make way for the water pipes to be placed.
![]() |
John gives Johnny instructions for the additional digging requirements |
![]() |
Digging deeper for the master bedroom/bath foundation |
![]() |
The water pipes will be located in these channels |
The last task of the day was to form up the current downstairs steps to make them wider. Tomorrow, concrete will be poured and the additional area leveled off.
![]() |
John watches as Chris creates the formwork for the steps |
![]() |
Completed formwork - ready for concreting |
I'm hoping the weather will continue to be good tomorrow and allow for yet another productive day.