Yesterday, the guys got started on building the walls for the master bedroom/bathroom and completed 4 courses of block on the side and back walls. Johnny had to work out the additional pipe joints as the back wall was being built.
While all of that was going outside in the cold, windy air, Luis continued the installation of the ceiling and walls in the downstairs bedroom.
Chris drills holes for metal support rods to be placed |
Tony begins building the back wall |
Luis installs the ceiling |
Chris cuts a piece of block to allow access for electrical pipe |
First row of block laid for side wall |
A look at the building process - mortar is put down before the block is laid |
Tony places the block on the mortar foundation |
Tony fills the side and top joints with mortar |
Johnny works on the PVC pipe fittings |
First row of block laid for back wall |
Third row of block done for both walls |
Tony gets additional mortar |
Fourth row of block completed and end block for fifth row in place to set levels |
Ceiling installed and most walls up by the end of day |
Troy and I pulled electrical wires until 10:45pm, so I decided to write yesterday's post this morning. Today, Chris and Tony will continue working on the outside walls, while Luis finishes installing the remaining wall board in the downstairs bedroom. I have to pack up more stuff in my current radio room and move it up here with the rest of the things that have taken up residence with me and my computers!